BAZA KEDUNGU: First Floor Construction Started

1 April 2026 Bali Baza Bali Baza
BAZA KEDUNGU: First Floor Construction Started

🏗 BAZA KEDUNGU — Construction Report for March 2026

📌 Foundation and preparatory works

Block 1:

  • Pile driving completed
  • Backfilling completed
  • Lean concrete base installed
  • Foundation beam reinforcement cages fabricated

Block 3:

  • Lean concrete base installed
  • Pile heads cut off

Block 4:

  • Pile heads partially cut off

Pool basin:

  • Pile heads partially cut off

📌 Underground structures

Block 2:

  • Basement walls concreted
  • Formwork for the underground level slab installed
  • Preparation for slab installation completed

📌 Transition to the above-ground phase

Block 2:

  • Floor slab at elevation 0.000 poured
  • Installation of 1st floor columns started
  • Reinforcement of vertical structures in progress

📌 Reinforcement works

  • Fabrication of reinforcement cages (Blocks 1 and 3)
  • Preparation of elements for further concreting

📊 March summary

Key stages of piling and foundation works have been completed. The underground part of Block 2 has been fully formed. The project has moved into the above-ground construction stage — the 1st floor has started. Works are being carried out in parallel across several blocks.

🔜 Plan for April

  • Block 2: construction of 1st floor structures
  • Blocks 1 and 3: installation of the basement floor slab
  • Block 1: construction of basement walls

The project is in an active construction phase. Works are continuing without توقف.