BAZA KEDUNGU: All Three Blocks in Progress

8 June 2026 Bali Baza Bali Baza
BAZA KEDUNGU: All Three Blocks in Progress

BAZA KEDUNGU

construction report for May 2026

All three blocks gained momentum in May. Block 2 topped off the second floor and moved to the third. Block 1 caught up—closed the basement and rose to the first floor. Block 3 completed the basement walls.

🟦 Block 2 — third floor

  • Walls and columns of the 2nd floor cast in concrete
  • 2nd-floor slab reinforced and poured
  • Rebar cages for 3rd-floor walls and columns fabricated and installed
  • Basement walls waterproofed

🟨 Block 1 — rising above ground

  • Basement walls cast in concrete
  • Basement slab poured
  • Rebar cages and formwork for 1st-floor walls and columns installed
  • 1st-floor slab poured

🟧 Block 3 — basement closed out

  • Basement walls cast in concrete
  • Preparing to reach level 0.000 (ground level)

📊 May summary

All three blocks are active simultaneously. Block 2 reached the third floor, Block 1 completed the first floor, Block 3 finished the basement walls. Waterproofing on Block 2 is complete—protected from water. We’re on schedule.

🔜 Plans for June

  • Block 2: 3rd-floor concrete works, progressing to the roof
  • Block 1: erecting the 2nd floor
  • Block 3: basement slab, reaching level 0.000
  • Waterproofing basements of Blocks 1 and 3
  • Continuing works on the pool shell

Developer

Bali Baza
Developer