BAZA KEDUNGU: All Three Blocks in Progress

BAZA KEDUNGU
construction report for May 2026
All three blocks gained momentum in May. Block 2 topped off the second floor and moved to the third. Block 1 caught up—closed the basement and rose to the first floor. Block 3 completed the basement walls.
🟦 Block 2 — third floor
- Walls and columns of the 2nd floor cast in concrete
- 2nd-floor slab reinforced and poured
- Rebar cages for 3rd-floor walls and columns fabricated and installed
- Basement walls waterproofed
🟨 Block 1 — rising above ground
- Basement walls cast in concrete
- Basement slab poured
- Rebar cages and formwork for 1st-floor walls and columns installed
- 1st-floor slab poured
🟧 Block 3 — basement closed out
- Basement walls cast in concrete
- Preparing to reach level 0.000 (ground level)
📊 May summary
All three blocks are active simultaneously. Block 2 reached the third floor, Block 1 completed the first floor, Block 3 finished the basement walls. Waterproofing on Block 2 is complete—protected from water. We’re on schedule.
🔜 Plans for June
- Block 2: 3rd-floor concrete works, progressing to the roof
- Block 1: erecting the 2nd floor
- Block 3: basement slab, reaching level 0.000
- Waterproofing basements of Blocks 1 and 3
- Continuing works on the pool shell