ORIGINS NUANU: First Villa Goes Vertical

ORIGINS NUANU
construction report for May 2026
In May the project moved from preparation to active construction. Pile head cutting finished, we went into the ground for foundations and started the superstructure — at Villa No.1 the ground-floor slab is poured and column rebar cages are in place.
⚙️ Preparation and earthworks
- Site cleared (root area)
- Pile heads cut to design level
- Excavation completed for foundation beams and slabs
🔌 MEP
- Underground services laid on Villas No.1 and No.2 prior to slab works
🧱 Foundations
- Rebar cages for foundation beams and slabs fabricated and installed on Villas No.1–No.4
- Lean concrete blinding completed on Villas No.1 and No.2
- Ground-floor slab cast on Villa No.1
🏛 Superstructure start
- Column rebar cages fabricated and installed on Villa No.1 — the first villa is going up
📊 May summary
Pile head cutting is complete. Foundation cages are ready on four villas, blinding is done on two, and Villa No.1 already has its slab and column rebar. Works are on schedule.
🔜 Plans for June
- Pour foundation slabs on Villas No.2–No.4
- Cast first-floor columns on Villa No.1
- Start column reinforcement on Villa No.2
- Continue MEP installation on subsequent villas