BAZA KEDUNGU: Construction Reaches a New Stage

🏗 BAZA KEDUNGU — weekly construction site report
Sharing the progress from the past week 🌟
✅ Completed / significant progress
Block 2:
- Lean concrete base installation — 90%
- Fabrication of reinforcement cages for tie beams — 100%
🔄 In progress
Block 2:
- Installation of reinforcement cages for foundation beams — 60%
- Compaction of the base under the floor slab — 80%
- Pile head trimming — 60%
📌 Next steps
- Completion of pile head trimming for Block 2
- Completion of foundation beam works
- Preparation for concrete works
- Transition to the next stage of structural works
The work is proceeding on schedule, contractors are on site, and the pace remains high.
The transition to concrete works is the next key stage 🏗



