Baza Kedungu: Construction Is in Full Swing

15 December 2025 Bali Baza Bali Baza
Baza Kedungu: Construction Is in Full Swing

We’re sharing the latest update from the Baza Kedungu project construction site.

Work is progressing actively across several blocks at once — the pace is steady, and the process is well organized.

WHAT HAS BEEN COMPLETED RECENTLY:

  • The internal site road has been reinforced
  • About 250 m³ of soil has been removed (Block 1)
  • Design levels have been prepared for pile driving
  • Pile driving has been fully completed on Block 3
  • Earthworks have started on Block 2
  • Pile driving has started on Blocks 4 and 1
  • The pile-driving rig has been relocated

Working on site simultaneously:

2 excavators and 4 dump trucks, allowing work to proceed in parallel and without downtime.

PLAN FOR THE COMING WEEK:

  • Driving about 50 piles — Block 1
  • Excavation and removal of about 500 m³ of soil — Block 3

Additionally, we note:

✅ The PBG for the Baza Kedungu project has been signed — construction is being carried out within the approved project documentation.

Attaching a fresh video from the construction site 🔥