Baza Kedungu: Construction Is in Full Swing

We’re sharing the latest update from the Baza Kedungu project construction site.
Work is progressing actively across several blocks at once — the pace is steady, and the process is well organized.
WHAT HAS BEEN COMPLETED RECENTLY:
- The internal site road has been reinforced
- About 250 m³ of soil has been removed (Block 1)
- Design levels have been prepared for pile driving
- Pile driving has been fully completed on Block 3
- Earthworks have started on Block 2
- Pile driving has started on Blocks 4 and 1
- The pile-driving rig has been relocated
Working on site simultaneously:
2 excavators and 4 dump trucks, allowing work to proceed in parallel and without downtime.
PLAN FOR THE COMING WEEK:
- Driving about 50 piles — Block 1
- Excavation and removal of about 500 m³ of soil — Block 3
Additionally, we note:
✅ The PBG for the Baza Kedungu project has been signed — construction is being carried out within the approved project documentation.
Attaching a fresh video from the construction site 🔥