Baza Kedungu: Construction Continues Through Holidays

The New Year atmosphere is everywhere, but at the Baza Kedungu construction site, work continues at its usual pace — with no pauses or days off.
The holiday period is not slowing the process: the team is on site, machinery is operating, and the schedule is being maintained.
Now to the facts 👇Weekly construction report for Baza Kedungu
🔹 Earthworks:
- Block 1 — 100%
- Block 2 — 100%
- Block 3 — 100%
- Block 4 — 70%
- Pool — 70%
🔹 Piling works:
- Pool — 13 piles
- Block 4 — 100%
- Block 3 — 100%
🔹 Structural works:
- Drainage ditch installation
Plan for next week:
- Completion of earthworks
- Piling works up to 70%
- Installation of shelters and the electrical switchboard room
We keep moving forward — steadily, systematically, and on schedule.
Thanks to the entire on-site team for their work and responsibility 💪🤍