The New Year atmosphere is everywhere, but at the Baza Kedungu construction site, work continues at its usual pace — with no pauses or days off.

The holiday period is not slowing the process: the team is on site, machinery is operating, and the schedule is being maintained.

Now to the facts 👇Weekly construction report for Baza Kedungu

🔹 Earthworks:

  • Block 1 — 100%
  • Block 2 — 100%
  • Block 3 — 100%
  • Block 4 — 70%
  • Pool — 70%

🔹 Piling works:

  • Pool — 13 piles
  • Block 4 — 100%
  • Block 3 — 100%

🔹 Structural works:

  • Drainage ditch installation

Plan for next week:

  • Completion of earthworks
  • Piling works up to 70%
  • Installation of shelters and the electrical switchboard room

We keep moving forward — steadily, systematically, and on schedule.

Thanks to the entire on-site team for their work and responsibility 💪🤍