ORIGINS: Construction Progress Continues

28 January 2026 Bali Baza Bali Baza
ORIGINS: Construction Progress Continues

🏗 ORIGINS — construction status and work progress‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

The preparation stage has been completed, and work is proceeding steadily without pauses.‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

🏗 Earthworks‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

Total work volume:‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

~8,000 m³ of soil‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

The plot has a complex curvilinear geometry, so a combined scheme is being used:‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

  • excavation is being carried out on part of the site
  • backfilling is being done on the remaining part‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

What was completed over the past week (fact):‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

  • soil delivery and backfilling of voids — 600 m³
  • soil compaction
  • grading works‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

🪨 Piling works‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

  • reinforced concrete piles have been ordered
  • production time — 25 days
  • delivery to the site — ≈ 5 days
  • pile driving will start immediately after delivery‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

👉 Piling works will be carried out in parallel with the earthworks (approximately 2 months).‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

🏗 Structural works (reinforced concrete)‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

As soon as the first pile fields are ready, the contractor will move onto the site without delay and begin the reinforced concrete structural works.‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

📈 Project dynamics‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

  • works have already started and are continuing without توقف
  • construction pace will increase during the current month
  • the project has entered a stable construction cycle‌‍​‍‌⁠‍​​⁠‍‍​‍⁠⁠‌‍‌‌‌‍⁠‍​‍⁠⁠‌‍⁠‍‌‍‌‌‌⁠‌⁠‌⁠​⁠​‍⁠⁠‌‍⁠⁠‌⁠​‍‌‍‍‌‌‍‌⁠‌‍‍‌‌‍⁠‍‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠​⁠‌⁠‌​‌⁠​‍‌⁠‌‌‌‍​⁠‌⁠‌​‌‍‍‌‌‍⁠⁠‌‍⁠‍​‍⁠‌‌⁠​​‌⁠​‍‌‍⁠⁠‌‍‌⁠‌⁠​‍‌‍‌‌‌⁠​⁠‌⁠​⁠​‍⁠‌‌‍​⁠‌‍⁠⁠‌‍⁠‍‌⁠‌​‌‍‍‌‌‍⁠‍‌⁠‌‌‌‍‌‌‌⁠​⁠

Developer

Bali Baza
Developer
Bali Baza
View developer

Residential complex

Residential complex
Origins
View complex

Units in this complex

More from Bali Baza