Monolithic Works Begin: First Concrete Poured

23 February 2026 Bali Baza Bali Baza
Monolithic Works Begin: First Concrete Poured

Hello everyone!

🔔 Main news of the week

We poured the first concrete! The start of monolithic works has officially taken place: after completing the piling and preparatory stages, the formation of the project's load-bearing structures has begun — this is an important milestone.

📍 Construction site in Kedungu — work status

🏗 Monolithic slab at elevation -3.700 (Blocks 1–2)

  • Reinforcement of the reinforced concrete slab completed
  • Formwork installation completed
  • Concrete pouring completed

Total pouring volume: 139 m³ of concrete

🪨 Piling works (Blocks 1 and 3)

  • Pile head trimming completed

(preparation of pile heads for further monolithic works)

🌍 Foundation base preparation (Block 1)

  • Foundation base filling completed

(formation of the base for the next construction stages)

What does this mean for the project?

  • Construction has entered the active phase
  • We are on schedule, with a good pace
  • The monolithic frame has started taking shape

We continue working according to plan: next comes the continuation of monolithic works and preparation of the next sections for pouring.