Construction on Schedule: Latest Report

23 January 2026 Bali Baza Bali Baza
Construction on Schedule: Latest Report

We are sharing the latest work status on site:

✅ Completed

  • Earthworks completed for all residential blocks (except the pool area)
  • Excess soil fully removed from the site
  • Storage facilities and the construction camp have been built
  • Hard surfacing of access roads completed
  • Permanent power supply connected
  • Piles driven for the residential blocks and pool
  • except for 42 piles in Block 1 (scheduled for the next stage)
  • Reinforcement delivered for concrete works

🔄 In progress

  • Pile cutting
  • Fabrication of reinforcement cages for the foundations

📌 Planned

  • Completion of driving the remaining 42 piles in Block 1
  • Preparation for foundation concrete works
  • Transition to the next stage of structural works

The project is progressing according to the approved schedule.

The on-site team is working at full pace — moving confidently toward the next stage of construction 🚀