ORIGINS: Construction Progress Continues

🏗 ORIGINS — construction status and work progress
The preparation stage has been completed, and work is proceeding steadily without pauses.
🏗 Earthworks
Total work volume:
~8,000 m³ of soil
The plot has a complex curvilinear geometry, so a combined scheme is being used:
- excavation is being carried out on part of the site
- backfilling is being done on the remaining part
What was completed over the past week (fact):
- soil delivery and backfilling of voids — 600 m³
- soil compaction
- grading works
🪨 Piling works
- reinforced concrete piles have been ordered
- production time — 25 days
- delivery to the site — ≈ 5 days
- pile driving will start immediately after delivery
👉 Piling works will be carried out in parallel with the earthworks (approximately 2 months).
🏗 Structural works (reinforced concrete)
As soon as the first pile fields are ready, the contractor will move onto the site without delay and begin the reinforced concrete structural works.
📈 Project dynamics
- works have already started and are continuing without توقف
- construction pace will increase during the current month
- the project has entered a stable construction cycle