ORIGINS NUANU: March 2026 Construction Update

1 April 2026 Bali Baza Bali Baza
ORIGINS NUANU: March 2026 Construction Update

🏗 ORIGINS NUANU — Construction Report for March 2026

📊 Earthworks

Total fill volume for March: ~5,740 m³

  • Backfilling completed
  • Site grading carried out
  • Soil delivery to the site organized

📌 Infrastructure Preparation

  • Soil compaction completed
  • Base prepared for future roads and driveways
  • Void filling completed using gravel sand

📊 March Summary

The site has been prepared for the transition to the next stages of construction. Foundations for the road network have been formed. Key soil stabilization works have been completed.

🔜 Plan for April

  • Completion of filling and soil compaction
  • Start of pile driving (planned to be completed in April)
  • Start of pile cutting
  • Start of monolithic and foundation works for the villas on Spring Alley (upper terrace)

The project is moving from the earthworks stage into the pile and foundation stage. The pace is accelerating.