Fresh update from the Amani Melasti site
27 July 2026

Sharing a fresh update from the Amani Melasti construction site.
In June, works progressed at a steady pace — key structural milestones were completed while masonry advanced in parallel. The project is entering the final stage of concrete works: the load-bearing frame across all three sections is approaching roof level.
As of now:
- Section 1 — vertical structures of the second floor and the third-floor slab are completed. Concreting of the third-floor verticals is in progress.
- Section 2 — the fourth-floor slab and vertical structures are fully completed. Reinforcement of the fifth-floor slab is underway, with masonry continuing on the second floor.
- Section 3 — the fourth-floor verticals and masonry on the second floor are completed. Concreting of the fifth-floor slab and fifth-floor verticals is in progress — the final level of the project’s structural frame.
Planned on site in July:
- Section 1 — erection of the third-floor verticals, installation of the fourth-floor slab, horizontal waterproofing of the first floor, and the start of masonry on the second floor.
- Sections 2 and 3 — erection of the fifth-floor verticals and installation of the roof slab. These two sections will reach roof level first. Masonry on the third floor will continue in parallel.
The project is steadily moving toward completion of the structural phase. We’ll share the next construction progress update soon.