Our project is growing before your eyes! Fresh figures from the Construction Director, backed by the team’s daily work:
01/ Villa structure – 52%
02 / Pools – 36%
03 / MEP and utilities – 60%
04 / Tanks and soak pits (resapans) – 60%
In mid‑July we start wall masonry on the first units. By late August, structural works on all 18 units will be fully completed. For now—watch the video! 🎬