BAZA KEDUNGU: First Floor Construction Started

🏗 BAZA KEDUNGU — Construction Report for March 2026
📌 Foundation and preparatory works
Block 1:
- Pile driving completed
- Backfilling completed
- Lean concrete base installed
- Foundation beam reinforcement cages fabricated
Block 3:
- Lean concrete base installed
- Pile heads cut off
Block 4:
- Pile heads partially cut off
Pool basin:
- Pile heads partially cut off
📌 Underground structures
Block 2:
- Basement walls concreted
- Formwork for the underground level slab installed
- Preparation for slab installation completed
📌 Transition to the above-ground phase
Block 2:
- Floor slab at elevation 0.000 poured
- Installation of 1st floor columns started
- Reinforcement of vertical structures in progress
📌 Reinforcement works
- Fabrication of reinforcement cages (Blocks 1 and 3)
- Preparation of elements for further concreting
📊 March summary
Key stages of piling and foundation works have been completed. The underground part of Block 2 has been fully formed. The project has moved into the above-ground construction stage — the 1st floor has started. Works are being carried out in parallel across several blocks.
🔜 Plan for April
- Block 2: construction of 1st floor structures
- Blocks 1 and 3: installation of the basement floor slab
- Block 1: construction of basement walls
The project is in an active construction phase. Works are continuing without توقف.