Construction on Track: Foundation Nearly Complete

This month on site: ✔️ 94 m³ of concrete poured into the foundation slab — 90% complete ✔️ 16 first-floor columns concreted ✔️ The first-floor stairwell and elevator module shaft concreted ✔️ Villa foundation slab — 60% complete ✔️ Formwork installation and reinforcement of the villa pool structures are underway
Step by step, the structure is taking shape — steady progress and a solid foundation are in place!