Minori: Construction 60% Complete

12 March 2026 Eco Invest Group Eco Invest Group
Minori: Construction 60% Complete

Dear partners,

We continue to share regular and transparent updates on the construction progress of the Minori project — only facts and real progress.

As of today, the project is 60% complete, with all key stages being carried out according to schedule.

Current completion: 60%

▪️ Foundation works — 100%

▪️ Construction of load-bearing reinforced concrete structures — 100%

▪️ Internal engineering systems (rough installation of water supply, sewage, and electrical systems) — 50%

▪️ External engineering systems (installation of water supply, sewage, stormwater drainage, and electrical systems) — 10%

▪️ Pool construction — 95%

▪️ Fence construction — 10%

▪️ Partition installation — 95%

▪️ Rough wall finishing works — 70%

▪️ Rough floor finishing works — 10%

▪️ Roof installation — 90%

What was completed over the last period:

▪️ Reinforced concrete structures — +1%

▪️ Internal engineering systems (rough installation of water supply, sewage, and electrical systems) — +12%

▪️ External engineering systems (installation of water supply, sewage, stormwater drainage, and electrical systems) — +10%

▪️ Pool construction — +25%

▪️ Fence construction — +10%

▪️ Partition installation — +15%

▪️ Rough wall finishing works — +20%

▪️ Rough floor finishing works — +10%

▪️ Roof installation — +25%

Thank you for your trust and support. We look forward to many successful deals ahead and a large number of satisfied clients.