Minori: Construction 60% Complete

Dear partners,
We continue to share regular and transparent updates on the construction progress of the Minori project — only facts and real progress.
As of today, the project is 60% complete, with all key stages being carried out according to schedule.
Current completion: 60%
▪️ Foundation works — 100%
▪️ Construction of load-bearing reinforced concrete structures — 100%
▪️ Internal engineering systems (rough installation of water supply, sewage, and electrical systems) — 50%
▪️ External engineering systems (installation of water supply, sewage, stormwater drainage, and electrical systems) — 10%
▪️ Pool construction — 95%
▪️ Fence construction — 10%
▪️ Partition installation — 95%
▪️ Rough wall finishing works — 70%
▪️ Rough floor finishing works — 10%
▪️ Roof installation — 90%
What was completed over the last period:
▪️ Reinforced concrete structures — +1%
▪️ Internal engineering systems (rough installation of water supply, sewage, and electrical systems) — +12%
▪️ External engineering systems (installation of water supply, sewage, stormwater drainage, and electrical systems) — +10%
▪️ Pool construction — +25%
▪️ Fence construction — +10%
▪️ Partition installation — +15%
▪️ Rough wall finishing works — +20%
▪️ Rough floor finishing works — +10%
▪️ Roof installation — +25%
Thank you for your trust and support. We look forward to many successful deals ahead and a large number of satisfied clients.