Lyvin Gardens: key construction milestones in March

🏗️Lyvin Gardens construction report for March 2026
Colleagues, we are sharing our construction report for the Lyvin Gardens complex for March.
Key updates for March:
- The complex is taking on a clear architectural silhouette
- Line A: the first-floor structure is complete
- Line B: roofs are fully completed
- Line C: brick walls have been erected
- Line D: roof covering installation is nearing completion
- The pool area is close to completion
- A change of contractor for finishing works is underway: an audit and handover of the construction stage are currently in progress
- The start of finishing works is scheduled for next month
Plans for April:
- Installation of engineering systems
- Waterproofing
- Plastering works