Drilling piles: 30 per day despite the rains

We are installing drilled piles for Building 2.
The building is large — the project will include a total of 271 piles with a 500 mm diameter and 52 piles with a 300 mm diameter.
Installing a pile field of this size usually takes a long time, but the construction team expects to increase productivity to 30 piles per day and complete the work within 2–3 weeks.
By mid-November, we will be able to see whether we can meet this target, especially given the approaching rainy season, which may slow down the pace of work.