ARDHANA: construction update from May 6

7 May 2026 High Quality Construction High Quality Construction

πŸ—οΈ Sharing the latest updates from the ARDHANA construction site as of May 06, 2026!β€Œβ€β€‹β€β€Œβ β€β€‹β€‹β β€β€β€‹β€β β β€Œβ€β€Œβ€Œβ€Œβ€β β€β€‹β€β β β€Œβ€β β€β€Œβ€β€Œβ€Œβ€Œβ β€Œβ β€Œβ β€‹β β€‹β€β β β€Œβ€β€‹β€Œβ€Œβ β€‹β€β€Œβ€β€Œβ€‹β€Œβ€β€β€‹β€Œβ€β€‹β€Œβ€Œβ€β β€β€Œβ€β€‹β€Œβ€‹β€β β€Œβ€Œβ€β€‹β β€Œβ€β β β€Œβ€β β€β€Œβ β€‹β β€Œβ β€Œβ€‹β€Œβ β€‹β€β€Œβ β€Œβ€Œβ€Œβ€β€‹β β€Œβ β€Œβ€‹β€Œβ€β€β€Œβ€Œβ€β β β€Œβ€β β€β€‹β€β β€Œβ€Œβ β€Œβ€Œβ€Œβ β€‹β€‹β€Œβ€β€Œβ€‹β€Œβ€β€‹β€Œβ€Œβ β€Œβ€‹β€Œβ€β€Œβ€Œβ€‹β€β β€Œβ€Œβ€β€Œβ€β€Œβ β€‹β€β€Œβ€β β β€Œβ€β β€Œβ€‹β€β β€Œβ€Œβ€β β€Œβ€Œβ€β€‹β€Œβ€Œβ β€β€Œβ€‹β€β β€Œβ€‹β β€Œβ€

🏒 Building A:β€Œβ€β€‹β€β€Œβ β€β€‹β€‹β β€β€β€‹β€β β β€Œβ€β€Œβ€Œβ€Œβ€β β€β€‹β€β β β€Œβ€β β€β€Œβ€β€Œβ€Œβ€Œβ β€Œβ β€Œβ β€‹β β€‹β€β β β€Œβ€β€‹β€Œβ€Œβ β€‹β€β€Œβ€β€Œβ€‹β€Œβ€β€β€‹β€Œβ€β€‹β€Œβ€Œβ€β β€β€Œβ€β€‹β€Œβ€‹β€β β€Œβ€Œβ€β€‹β β€Œβ€β β β€Œβ€β β€β€Œβ β€‹β β€Œβ β€Œβ€‹β€Œβ β€‹β€β€Œβ β€Œβ€Œβ€Œβ€β€‹β β€Œβ β€Œβ€‹β€Œβ€β€β€Œβ€Œβ€β β β€Œβ€β β€β€‹β€β β€Œβ€Œβ β€Œβ€Œβ€Œβ β€‹β€‹β€Œβ€β€Œβ€‹β€Œβ€β€‹β€Œβ€Œβ β€Œβ€‹β€Œβ€β€Œβ€Œβ€‹β€β β€Œβ€Œβ€β€Œβ€β€Œβ β€‹β€β€Œβ€β β β€Œβ€β β€Œβ€‹β€β β€Œβ€Œβ€β β€Œβ€Œβ€β€‹β€Œβ€Œβ β€β€Œβ€‹β€β β€Œβ€‹β β€Œβ€

  • Ground & 1st floor: Main MEP and rough finishing works are completed! πŸ’ͺ Final finishing has started, window lintels and sink bases have been installed.
  • 2nd floor: Wall partitions are completed, rough wall finishing has begun.
  • Rooftop: We continue constructing the columns.β€Œβ€β€‹β€β€Œβ β€β€‹β€‹β β€β€β€‹β€β β β€Œβ€β€Œβ€Œβ€Œβ€β β€β€‹β€β β β€Œβ€β β€β€Œβ€β€Œβ€Œβ€Œβ β€Œβ β€Œβ β€‹β β€‹β€β β β€Œβ€β€‹β€Œβ€Œβ β€‹β€β€Œβ€β€Œβ€‹β€Œβ€β€β€‹β€Œβ€β€‹β€Œβ€Œβ€β β€β€Œβ€β€‹β€Œβ€‹β€β β€Œβ€Œβ€β€‹β β€Œβ€β β β€Œβ€β β€β€Œβ β€‹β β€Œβ β€Œβ€‹β€Œβ β€‹β€β€Œβ β€Œβ€Œβ€Œβ€β€‹β β€Œβ β€Œβ€‹β€Œβ€β€β€Œβ€Œβ€β β β€Œβ€β β€β€‹β€β β€Œβ€Œβ β€Œβ€Œβ€Œβ β€‹β€‹β€Œβ€β€Œβ€‹β€Œβ€β€‹β€Œβ€Œβ β€Œβ€‹β€Œβ€β€Œβ€Œβ€‹β€β β€Œβ€Œβ€β€Œβ€β€Œβ β€‹β€β€Œβ€β β β€Œβ€β β€Œβ€‹β€β β€Œβ€Œβ€β β€Œβ€Œβ€β€‹β€Œβ€Œβ β€β€Œβ€‹β€β β€Œβ€‹β β€Œβ€

🏒 Building B:β€Œβ€β€‹β€β€Œβ β€β€‹β€‹β β€β€β€‹β€β β β€Œβ€β€Œβ€Œβ€Œβ€β β€β€‹β€β β β€Œβ€β β€β€Œβ€β€Œβ€Œβ€Œβ β€Œβ β€Œβ β€‹β β€‹β€β β β€Œβ€β€‹β€Œβ€Œβ β€‹β€β€Œβ€β€Œβ€‹β€Œβ€β€β€‹β€Œβ€β€‹β€Œβ€Œβ€β β€β€Œβ€β€‹β€Œβ€‹β€β β€Œβ€Œβ€β€‹β β€Œβ€β β β€Œβ€β β€β€Œβ β€‹β β€Œβ β€Œβ€‹β€Œβ β€‹β€β€Œβ β€Œβ€Œβ€Œβ€β€‹β β€Œβ β€Œβ€‹β€Œβ€β€β€Œβ€Œβ€β β β€Œβ€β β€β€‹β€β β€Œβ€Œβ β€Œβ€Œβ€Œβ β€‹β€‹β€Œβ€β€Œβ€‹β€Œβ€β€‹β€Œβ€Œβ β€Œβ€‹β€Œβ€β€Œβ€Œβ€‹β€β β€Œβ€Œβ€β€Œβ€β€Œβ β€‹β€β€Œβ€β β β€Œβ€β β€Œβ€‹β€β β€Œβ€Œβ€β β€Œβ€Œβ€β€‹β€Œβ€Œβ β€β€Œβ€‹β€β β€Œβ€‹β β€Œβ€

  • Ground Floor: Waterproofing of the retaining wall is completed, slab works and MEP installation are underway.
  • 1st floor: Masonry and MEP are completed! Rough finishing is 70% complete, moving on to final finishing. Installation of sink bases is in progress.
  • 2nd floor: The columns have reached design strength, and slab concreting is actively underway.β€Œβ€β€‹β€β€Œβ β€β€‹β€‹β β€β€β€‹β€β β β€Œβ€β€Œβ€Œβ€Œβ€β β€β€‹β€β β β€Œβ€β β€β€Œβ€β€Œβ€Œβ€Œβ β€Œβ β€Œβ β€‹β β€‹β€β β β€Œβ€β€‹β€Œβ€Œβ β€‹β€β€Œβ€β€Œβ€‹β€Œβ€β€β€‹β€Œβ€β€‹β€Œβ€Œβ€β β€β€Œβ€β€‹β€Œβ€‹β€β β€Œβ€Œβ€β€‹β β€Œβ€β β β€Œβ€β β€β€Œβ β€‹β β€Œβ β€Œβ€‹β€Œβ β€‹β€β€Œβ β€Œβ€Œβ€Œβ€β€‹β β€Œβ β€Œβ€‹β€Œβ€β€β€Œβ€Œβ€β β β€Œβ€β β€β€‹β€β β€Œβ€Œβ β€Œβ€Œβ€Œβ β€‹β€‹β€Œβ€β€Œβ€‹β€Œβ€β€‹β€Œβ€Œβ β€Œβ€‹β€Œβ€β€Œβ€Œβ€‹β€β β€Œβ€Œβ€β€Œβ€β€Œβ β€‹β€β€Œβ€β β β€Œβ€β β€Œβ€‹β€β β€Œβ€Œβ€β β€Œβ€Œβ€β€‹β€Œβ€Œβ β€β€Œβ€‹β€β β€Œβ€‹β β€Œβ€

πŸ› οΈ General construction works:β€Œβ€β€‹β€β€Œβ β€β€‹β€‹β β€β€β€‹β€β β β€Œβ€β€Œβ€Œβ€Œβ€β β€β€‹β€β β β€Œβ€β β€β€Œβ€β€Œβ€Œβ€Œβ β€Œβ β€Œβ β€‹β β€‹β€β β β€Œβ€β€‹β€Œβ€Œβ β€‹β€β€Œβ€β€Œβ€‹β€Œβ€β€β€‹β€Œβ€β€‹β€Œβ€Œβ€β β€β€Œβ€β€‹β€Œβ€‹β€β β€Œβ€Œβ€β€‹β β€Œβ€β β β€Œβ€β β€β€Œβ β€‹β β€Œβ β€Œβ€‹β€Œβ β€‹β€β€Œβ β€Œβ€Œβ€Œβ€β€‹β β€Œβ β€Œβ€‹β€Œβ€β€β€Œβ€Œβ€β β β€Œβ€β β€β€‹β€β β€Œβ€Œβ β€Œβ€Œβ€Œβ β€‹β€‹β€Œβ€β€Œβ€‹β€Œβ€β€‹β€Œβ€Œβ β€Œβ€‹β€Œβ€β€Œβ€Œβ€‹β€β β€Œβ€Œβ€β€Œβ€β€Œβ β€‹β€β€Œβ€β β β€Œβ€β β€Œβ€‹β€β β€Œβ€Œβ€β β€Œβ€Œβ€β€‹β€Œβ€Œβ β€β€Œβ€‹β€β β€Œβ€‹β β€Œβ€

  • Septic tank: Nearing completion.
  • Stairs πŸͺœ: Work continues on three types! The spiral staircase is 80% complete (preparing for concreting), and formwork works have started for the L-shaped stairs.β€Œβ€β€‹β€β€Œβ β€β€‹β€‹β β€β€β€‹β€β β β€Œβ€β€Œβ€Œβ€Œβ€β β€β€‹β€β β β€Œβ€β β€β€Œβ€β€Œβ€Œβ€Œβ β€Œβ β€Œβ β€‹β β€‹β€β β β€Œβ€β€‹β€Œβ€Œβ β€‹β€β€Œβ€β€Œβ€‹β€Œβ€β€β€‹β€Œβ€β€‹β€Œβ€Œβ€β β€β€Œβ€β€‹β€Œβ€‹β€β β€Œβ€Œβ€β€‹β β€Œβ€β β β€Œβ€β β€β€Œβ β€‹β β€Œβ β€Œβ€‹β€Œβ β€‹β€β€Œβ β€Œβ€Œβ€Œβ€β€‹β β€Œβ β€Œβ€‹β€Œβ€β€β€Œβ€Œβ€β β β€Œβ€β β€β€‹β€β β€Œβ€Œβ β€Œβ€Œβ€Œβ β€‹β€‹β€Œβ€β€Œβ€‹β€Œβ€β€‹β€Œβ€Œβ β€Œβ€‹β€Œβ€β€Œβ€Œβ€‹β€β β€Œβ€Œβ€β€Œβ€β€Œβ β€‹β€β€Œβ€β β β€Œβ€β β€Œβ€‹β€β β€Œβ€Œβ€β β€Œβ€Œβ€β€‹β€Œβ€Œβ β€β€Œβ€‹β€β β€Œβ€‹β β€Œβ€