BREIG Speeds Up Pile Installation for Building 2

2 November 2025 BREIG BREIG
BREIG Speeds Up Pile Installation for Building 2

BREIG has started installing bored piles for Building 2.

The building is large — the project will include a total of 271 piles with a 500 mm diameter and 52 piles with a 300 mm diameter.

Installing a pile field of this size usually takes a long time, but BREIG’s construction division aims to increase productivity to up to 30 piles per day and complete the work within 2–3 weeks.

By mid-November, it will be possible to see whether the company can meet this target, especially given the approaching rainy season, which may slow down the pace of work.

More from BREIG