🔥🔥🔥 AMANI Melasti construction progress for March 2026

We are sharing the latest updates from the AMANI Melasti construction site for March.

In March, Ramadan took place in Bali, and during this period construction activity traditionally slows down. Many workers travel to other islands to be with their families, so some processes on site are temporarily paused. This is standard practice for the region and is taken into account in advance in the overall project schedule.

Construction has now resumed. The team is gradually returning to the site, and starting from April 4, the project has fully returned to normal operations. This will allow a stable construction pace to be restored and the project to continue according to plan.

🔹 In April, the first section is scheduled for installation of the second-floor slab.

🔹 For the second section, the plan includes construction of the first-floor vertical structures, installation of the second-floor slab, as well as horizontal waterproofing on the technical floor.

🔹 For the third section, the plan includes installation of the third-floor slab, construction of the third-floor vertical structures, and horizontal waterproofing on the first floor.

Thus, in April the project is moving into an active phase of work across several sections at once, and in the next update we will be able to share even more visible progress on site.