Stroitelstvo idet po planu: fundament pochti gotov

18 November 2025 IJI Group IJI Group
Stroitelstvo idet po planu: fundament pochti gotov

V etom mesyatse na ploschadke: ✔️ V plitu fundamenta zalito 94 m³ betona — gotovo na 90% ✔️ Zabetonirovany 16 kolonn pervogo etazha ✔️ Zabetonirovany lestnichnaya kletka i shahta liftovogo modulya pervogo etazha ✔️ Plita fundamenta vill — vypolnena na 60% ✔️ Idet ustroystvo opalubki i armirovanie konstruktsiy basseynov vill

Shag za shagom struktura priobretaet formu — stabilnyy progress i krepkiy fundament zalozhen!