RAMADA Nusa Dua: Yanvarskie uspehi stroyki

3 Februari 2026 Teus Group Teus Group
RAMADA Nusa Dua: Yanvarskie uspehi stroyki

🔥Delimsya obnovleniyami so stroitelnoy ploschadki RAMADA Nusa Dua za yanvar.

🏗

🔹Na obekte zaversheny raboty po razrabotke kotlovana pod zdanie apartamentov. Posle zaversheniya zemlyanyh rabot proekt pereshel k sleduyuschemu etapu podgotovki stroitelnoy ploschadki.

🔹V nastoyaschiy moment vypolnyayutsya podgotovitelnye raboty: podklyuchenie stroitelnoy ploschadki k elektrosetyam PLN, organizatsiya vodosnabzheniya cherez PDAM, a takzhe nachalo rabot po ustroystvu postoyannogo ograzhdeniya kompleksa.

🔹Parallelno vedetsya organizatsiya stroitelnoy ploschadki — stroitelstvo lagerya dlya rabochih i shtaba stroitelstva, formirovanie neobhodimoy infrastruktury dlya dalneyshih etapov realizatsii proekta.

🔹Odnovremenno prodolzhayutsya raboty po proektirovaniyu i soglasovaniyu rabochey dokumentatsii.

Pangwangun

Teus Group
Pangwangun
Teus Group
3.3keandalan Balinsky · 0 puput
Cingak pangwangun

Kompleks hunian

Kompleks hunian
Ramada Nusa Dua
Cingak kompleks

Unit ring kompleks puniki

Sane lianan saking Teus Group