Minori: Stroitelstvo zaversheno na 60% — progress

Uvazhaemye partnery,
My prodolzhaem delitsya regulyarnymi i prozrachnymi obnovleniyami o hode stroitelstva proekta Minori — tolko fakty i realnyy progress.
Na segodnyashniy den gotovnost proekta sostavlyaet 60%, pri etom vse klyuchevye etapy realizuyutsya v sootvetstvii s grafikom.
Tekuschaya gotovnost: 60%
▪️ Ustroystvo fundamentov — 100%
▪️ Vozvedenie nesuschih zhelezobetonnyh konstruktsiy — 100%
▪️ Vnutrennie inzhenernye seti (chernovoy montazh vodosnabzheniya, kanalizatsii i elektriki) — 50%
▪️ Naruzhnye inzhenernye seti (montazh vodosnabzheniya, kanalizatsii, otvoda dozhdevoy vody i elektriki) — 10%
▪️ Stroitelstvo basseynov — 95%
▪️ Stroitelstvo zaborov — 10%
▪️ Montazh peregorodok — 95%
▪️ Chernovye otdelochnye raboty sten — 70%
▪️ Chernovye otdelochnye raboty polov — 10%
▪️ Montazh krovli — 90%
Chto bylo vypolneno za posledniy period:
▪️ Vozvedenie zhelezobetonnyh konstruktsiy — +1%
▪️ Vnutrennie inzhenernye seti (chernovoy montazh vodosnabzheniya, kanalizatsii i elektriki) — +12%
▪️ Naruzhnye inzhenernye seti (montazh vodosnabzheniya, kanalizatsii, otvoda dozhdevoy vody i elektriki) — +10%
▪️ Stroitelstvo basseynov — +25%
▪️ Stroitelstvo zaborov — +10%
▪️ Montazh peregorodok — +15%
▪️ Chernovye otdelochnye raboty sten — +20%
▪️ Chernovye otdelochnye raboty polov — +10%
▪️ Montazh krovli — +25%
Blagodarim vas za doverie i podderzhku. My rasschityvaem na mnozhestvo uspeshnyh sdelok vperedi i bolshoe kolichestvo dovolnyh klientov.