ARDHANA: obnovlenie so stroyploschadki ot 6 maya

7 Mei 2026 High Quality Construction High Quality Construction
ARDHANA: obnovlenie so stroyploschadki ot 6 maya

🏗️ Delimsya novostyami so stroyploschadki ARDHANA ot 06 maya 2026!

🏢 Zdanie A:

  • Ground & 1-y etazh: Osnovnye raboty po MEP i chernovoy otdelke zaversheny! 💪 Startovali chistovye raboty, ustanovleny okonnye peremychki i osnovaniya pod rakoviny.
  • 2-y etazh: Gotovy stenovye peregorodki, nachalas chernovaya otdelka sten.
  • Ruftop: Prodolzhaem vozvedenie kolonn.

🏢 Zdanie B:

  • Ground Floor: Zavershena gidroizolyatsiya podpornoy steny, vedetsya ustroystvo plity i montazh MEP.
  • 1-y etazh: Kladka i MEP gotovy! Chernovaya otdelka na 70%, pristupaem k chistovoy. Idet montazh osnovaniy pod rakoviny.
  • 2-y etazh: Kolonny nabrali proektnuyu prochnost, aktivno betoniruem plitu.

🛠️ Obschestroitelnye raboty:

  • Septik: Podhodit k zaversheniyu.
  • Lestnitsy 🪜: Prodolzhaem ustroystvo treh tipov! Vintovaya gotova na 80% (gotovimsya k betonirovaniyu), po L-obraznym nachaty raboty po opalubke.