ARDHANA: obnovlenie so stroyploschadki ot 6 maya

🏗️ Delimsya novostyami so stroyploschadki ARDHANA ot 06 maya 2026!
🏢 Zdanie A:
- Ground & 1-y etazh: Osnovnye raboty po MEP i chernovoy otdelke zaversheny! 💪 Startovali chistovye raboty, ustanovleny okonnye peremychki i osnovaniya pod rakoviny.
- 2-y etazh: Gotovy stenovye peregorodki, nachalas chernovaya otdelka sten.
- Ruftop: Prodolzhaem vozvedenie kolonn.
🏢 Zdanie B:
- Ground Floor: Zavershena gidroizolyatsiya podpornoy steny, vedetsya ustroystvo plity i montazh MEP.
- 1-y etazh: Kladka i MEP gotovy! Chernovaya otdelka na 70%, pristupaem k chistovoy. Idet montazh osnovaniy pod rakoviny.
- 2-y etazh: Kolonny nabrali proektnuyu prochnost, aktivno betoniruem plitu.
🛠️ Obschestroitelnye raboty:
- Septik: Podhodit k zaversheniyu.
- Lestnitsy 🪜: Prodolzhaem ustroystvo treh tipov! Vintovaya gotova na 80% (gotovimsya k betonirovaniyu), po L-obraznym nachaty raboty po opalubke.